TENDER PROJECT FOR THE WEST COMMERCIAL WHARF AT THE PORT OF MARÍN. PONTEVEDRA (SPAIN)

The Variant Tender Project is drafted to achieve a more optimal design for closing the wharf included in the Project with the existing Manuel Leirós Wharf. The project includes the extension of Leirós Wharf No. 2 by 30.37 metres with a draft of 12 metres at BMVE, to support, perpendicularly to the south, a 283-metre-long […]
TENDER PROJECT FOR WHARF NO. 9 AT RAOS IN THE PORT OF SANTANDER (SPAIN)

The Variant Tender Project is drafted to adapt the definition of the works to the available circular-cell formwork. The main characteristics of the wharf are: • Wharf length: 291 m • Draft: 18.25 m • Six caissons Additionally, it will be necessary to carry out ground improvement where the wharf will be founded, as well […]
TENDER PROJECT FOR MUELLE DE RIBERA I AT THE PORT OF CARBONERAS. ALMERÍA (SPAIN)

Variant Tender Project for adapting the caissons to the contractor’s formwork and designing the works required for the construction of a Ribera Wharf with a draft of 18.00 metres and a length of approximately 246 metres. The main characteristics of the wharf are: • Wharf length: 246 m • Draft: 18 m • Five caissons […]
VARIANT PROJECT FOR A CRUISE TERMINAL WHARF AT THE PORT OF ARRECIFE – PHASE 1. LANZAROTE (SPAIN)

Variant Project with adaptation of the internal structure and the lengths of the caissons to the contractor’s formwork. The works consist of the design of 2 types of caissons (type A and B) to achieve a 314.7 m extension of the wharf. The wharf will have a draft of 10 m. At the front of […]
VARIANT TENDER PROJECT FOR THE EXTENSION OF THE MSC TERMINAL AT THE PORT OF VALENCIA (SPAIN)

Variant Project with adaptation of the internal structure and the lengths of the caissons to the contractor’s formwork. The works consist of the design of 3 caissons to achieve an 80 m extension of the MSC wharf. Verification of the stability of the newly designed caissons is carried out, optimising the reinforcement and performing the […]
CONSTRUCTION PROJECT FOR THE EXTENSION OF THE PORT OF AVILÉS ON THE RIGHT BANK (SPAIN)

Construction Project for a Piled Wharf on the right bank of the Avilés Estuary. The main characteristics of the wharf are: • Wharf length: 504 m • 14 modules of 36 m with a 9×6 pile grid of 1.65 m diameter • Transverse and longitudinal beams acting as pile caps • Precast slabs of 0.35 […]
CONSTRUCTION PROJECT OF COMMERCIAL DOCKS AND ESPLANADES PROTECTED BY THE BOTAFOC DIKE IN THE PORT OF IBIZA (SPAIN)

Construction Project for docks protected by the Botafoc dike. The expansion consists of: • Two transverse docks, 200 m long and 30 m wide, designed with piles • Two dolphin berths located at the ends of the aforementioned docks • A 380 m long caisson-type longitudinal dock that forms a 75,000 m2 esplanade The draft […]
DRAFT IMPROVEMENT PROJECT FOR THE NORTH WESTERN QUAY EXTENSION AT THE PORT OF PALMA DE MALLORCA (SPAIN)

Construction Project to increase the theoretical draft from 7.16 m to 9 m in the westernmost 20 m of the North Western Quay Extension, adapting to functional and environmental constraints. In the remaining 196 m of the quay, restoration of the minimum theoretical draft of 9 m in silted areas. • Structural solution: reinforced concrete […]
VARIANT PROJECT FOR THE EXTENSION OF THE SOUTH QUAY IN THE PORT OF BARCELONA (SPAIN)

Variant Project with adaptation of the internal structure and the lengths of the caissons to the contractor’s formwork. The works are divided into three sections: • Extension of Álvarez de la Campa Quay, 198.22 m • Closure of the South Quay, 326.88 m • Extension of the South Quay, 98 m in length A yard […]
PORT OF FERROL EXPANSION PROJECT (OUTER PORT) – PHASE 2 – VARIANT SOLUTION, A CORUÑA (SPAIN)

Variant Project with adaptation of the internal structure and the lengths of the caissons to the formwork of the construction company. The works consist of: • Ribera Quay, 658.4 m long, formed by 14 caissons of 48.915 m in length • 3 caissons of 29.80 m at the Auxiliary Quay • 45 m of block […]