The project includes an optimization of all proposed marine infrastructure (subsea pipelines and jetties) and an alternatives study for the intake and discharge pipelines.
Specifically, the following tasks are carried out:
• Analysis and optimization of the project’s piers and jetties to reduce construction costs and make them economically viable.
• Analysis and alternatives study for the refinery’s intake and discharge pipelines, reducing their cost without compromising functionality and quality.
• Alternatives study for the project’s piers, consolidating them into a single infrastructure with a dual purpose:
• To serve as a temporary dry cargo pier during construction.
• Liquid cargo pier during the operational phase.