NEW LNG REGASIFICATION PLANT JETTY PRE-DESIGN
Jetties
- Start Date / End Date: 2011
- Place: HUELVA (SPAIN)
- Scope: Studies and reports
- Description:
Studies for the administrative concession for the construction of a mooring quay for LNG carriers
• Project carrier: Q-max•Freeboard length: 345 m•Breadth: 53,8 m•Depth: 34,7 m•Maximum draught: 12,0 m•Capacity: 266.000 m3• Jetty pre-design, analysing mainly the following aspects:1.Characterization of dredging material: sampling and laboratory analysis campaign2.Study of cargo waste and ship residue collection systems3.Study of interference of pipes and pipelines with existing roads