Simple Cycle Thermoelectric Power Plant. Gran Mariscal Industrial Complex. Ayacucho (Güiria – Venezuela). Equipment Unloading Wharf and Protective Breakwater

[bloque_categoria_proyecto]
Scope:
Basic Design
Location:
GÜIRIA- VENEZUELA

• Study of alternatives on site
• Equipment unloading wharf

• Vessel type: L = 77 m; B = 15 m; Dmax = 2.50 m
• Frontal unloading via gondola (L = 40 m + tractor head on land). Maximum equipment weight: 240 t
• Wharf:

•Temporary (Service life: 3 years)
•Type: precast plain concrete blocks
•Length: 40 m
•Platform: 30 m wide

• Access embankment:

•Wharf-to-land connection
•Type: slope (core, filter and outer layer with precast plain concrete blocks)
•Length: 200 m

•Wharf-to-land connection
•Type: slope (core, filter and outer layer with precast plain concrete blocks)
•Length: 200 m

• Maritime climate study
• Plan alternatives
• Length: 165 m, plus heads

• Type: slope

•All-in-one core
•Riprap filter
•Outer layer: precast plain concrete blocks