Marine works: Breakwater

  • Start Date / End Date: 2013
  • Place: ALMERIA, SPAIN
  • Scope: Tender Project
  • Description:

    The project consisted of adapting the Tender Project to the builder’s resources. The main modifications were:

          • A modification of the caisson cells to use circular cell caissons. The recalculation of the reinforcement considering the construction phase, towing and service phase.
          • A study on the towing of the caissons from Cartagena where they would be manufactured for depth availability reasons.
          • The recalculation of the superstructure, redesigning the pre-slabs over the anti-reflective windows.
          • Redesigning the anti-reflective windows, maintaining the Project reflection coefficient.


 IMAGES OF THE PROJECT

 
VARIABLE ALTERNATIVE CONSTRUCTION PROJECT FOR THE NEW WESTERN BREAKWATER (1ST PHASE). PORT OF ALMERIA
VARIABLE ALTERNATIVE CONSTRUCTION PROJECT FOR THE NEW WESTERN BREAKWATER (1ST PHASE). PORT OF ALMERIA

 RELATED PROJECTS

See more projects
DESIGN PROJECT OF ENLARGEMENT OF SANTA CRUZ DE LA PALMA BREAKWATER, LA...
ALTERNATIVE CONSTRUCTION PROJECT TO EXPAND THE PORT OF PLAYA BLANCA, L...
ALTERNATIVE TENDER PROJECT OF AGAETE HARBOUR EXPANSION, GRAN CANARIA (...