BENS SUBMARINE OUTFALL, A CORUÑA. DETAILED DESIGN OF CONSTRUCTION PROCESSES

[bloque_categoria_proyecto]
Scope:
Detailed design of construction processes
Location:
A CORUÑA (SPAIN)

This detailed design studies the construction processes and auxiliary elements for the sinking of the polyethylene section. The first section was carried out using pipe jacking.
The discharge pipeline in its deepest area is designed in PE100 and has the following characteristics:
• External diameter: 1,600 mm SDR 26
• Length: 360 m
• Maximum depth: 40.7 m

Specifically, the sinking process using floats and concrete sinkers, the slings to be used, the flanges, and the reinforcement to be implemented in the diffuser area are studied in detail.