MODIFIED PROJECT OF THE TRANSFER OF THE SUBMARINE OUTFALL OF THE SOUTHEAST COMMUNITY (GRAN CANARIA, SPAIN)
UNDERWATER PIPELINES
- Start Date / End Date: 2007
- Place: GRAN CANARIA, SPAIN
- Scope: Development of modified Construction Project
- Description:
Development of the modified project, proposing the changing of the route of the pipeline, which will go over the current dock, going out into the sea via a well created in a cell of one of the caissons.
It consists of:
•LAND section:• PE 100 pipe• Length 1047 m• Exterior diameter 900 mm• 27.6 mm thick• SDR of 33• Elevation: 4.377 m•SUBMARINE section:• PE 100 pipe• Exterior diameter 900 mm• 34.4 mm thickness• SDR 26• Length of 928 m, including the diffuser section.• Maximum depth: 26 m• Flow: 0.871 m3/s