- Start Date / End Date: 2008
- Place: SKIKDA, ALGERIA
- Scope: Project Construction
- Description: Viability study for changing the longitudinal profile, positioning pipes on the sea bed and then protecting them with rubble. This reduces the depth of the trench to be excavated.The following aspects were calculated based on the oceanographic parameters of the Construction Project:- Protection of pipes using rubble and filters- The required rigidity of pipeline with the new protectionWe also carried out a detailed study of the launch ramp for the pipes.