Marine civil works for the Repsol crude oil discharge jetty in the Outer Port of Langosteira

[bloque_categoria_proyecto]
Scope:
Construction project
Location:
A Coruña, Spain

New crude oil discharge jetty in the Outer Port of Punta Langosteira for 200,000 DWT vessels. The marine works of the jetty consist of a set of caissons with a depth of 24.50 and 29.00 m, forming the berthing platform, berthing dolphins, mooring dolphins, access bridge piers, and the substation and access road platforms. The guaranteed draft at the berth is 21.0 m.

The following works have been carried out:

  • Geotechnical stability analysis of the access road sections, the substation platform, the access bridge piers, the berthing platform, the berthing dolphins, and the mooring dolphins.
  • Structural analysis of all caissons.
  • Hydraulic stability analysis of the rock armour layers.
  • Design of the superstructure for all elements (structural and stability calculations).