PRELIMINARY PROJECT FOR THE EFFLUENT PIPELINE FROM THE CELLULOSE AND ENERGY PLANT IN PUNTA PEREIRA (URUGUAY)
UNDERWATER PIPELINES
- Start Date / End Date: 2008
- Place: PUNTA PEREIRA (URUGUAY)
- Scope: Preliminary Design for Bid
- Description:
Preliminary Design project of the effluent pipeline from the Punta Pereira paper mill (Uruguay). Part of the Complete Project of the paper mill, comprising one of its chapters.
The characteristics of the pipeline are:
• OD=1,400 mm• PE-80 SDR 33 Pipe• Q=2m3/s• Length 1,880 mThe following aspects of the conduit are studied:
• Design of diffuser and dumping process• Design of ballast weight• Installation process• Construction processes• Beaconing