TENDER PROJECT FOR THE CASABLANCA WASTE WATER TREATMENT PLANT OUTFALL (MOROCCO)

UNDERWATER PIPELINES

  • Start Date / End Date: 2011/2012
  • Place: CASABLANCA (MARRUECOS)
  • Scope: Tender Project
  • Description:

    The outfall tender project was designed. All of the alternatives proposed replacing the two base solution pipelines with a single larger-diameter pipeline with better hydraulic performance and the corresponding savings in cost and completion time.

    The characteristics common to all of the alternatives:

        •    Material: HA tunnel and the rest in PE100.
        •    Length of pipe jacking: 1,021 m
        •    Total length of the pipe (HA+PE): 2,200 m (option 0), 2,500 m (option 1) and 3,000 m (option 2).
        •    Flow rate: 11 m3/s

     

    The characteristics of each alternative:

        •    Alternative 1: ID = 1,966 mm. High pressure
        •    Alternative 2: ID = 2,200 mm.
        •    Alternative 3: ID = 2,200 mm.  High pressure

     

    The high pressure solutions were resolved with a specific sandwiched metal layer design compatible with the pipe jacking tunnel.

    On the other hand, a complete marine climate study was conducted.

     

     


 IMAGES OF THE PROJECT

 
TENDER PROJECT FOR THE CASABLANCA WASTE WATER TREATMENT PLANT OUTFALL (MOROCCO)
TENDER PROJECT FOR THE CASABLANCA WASTE WATER TREATMENT PLANT OUTFALL (MOROCCO)
TENDER PROJECT FOR THE CASABLANCA WASTE WATER TREATMENT PLANT OUTFALL (MOROCCO)

 RELATED PROJECTS

See more projects
PUNTA YEGUAS OUTFALL, MONTEVIDEO (URUGUAY)...
INTAKE AND OUTFALL PIPELINES FOR THE SANITATION AND SUPPLY SYSTEM IN T...
MARINE CLIMATE AND DILUTION STUDY TO FIND ALTERNATIVE LOCATIONS FOR TH...