UNDERWATER PIPELINES OF THE CCC OF KOUDIET (ALGERIA)

UNDERWATER PIPELINES

  • Start Date / End Date: 2008/2009
  • Place: KOUDIET (ARGELIA)
  • Scope: Construction Project
  • Description:

    The project defines the underwater pipelines for the intake refrigeration circuit for the CCC of Koudiet in Algeria.

    The characteristics of the intake pipelines are:

        •    Design: 4 pipelines of PE-100
        •    Interior Diameter: 2400 mm
        •    Length: between 394 and 437 m
        •    Average Depth: 15 m
        •    Flow rate of the refrigeration system: 27.77 m3/s, with a design flow rate of 41.67 m3/s, from the safety side
    Additionally the design of the intake structure in PRFV
     

    In the project it is also calculated the protection of the marine platform where the pumps are located.

     

     


 IMAGES OF THE PROJECT

 
UNDERWATER PIPELINES OF THE CCC OF KOUDIET (ALGERIA)
Intake tower, intake structure
GRP Intake tower
PE pipes sinking procedure
UNDERWATER PIPELINES OF THE CCC OF KOUDIET (ALGERIA)

 RELATED PROJECTS

See more projects
PUNTA YEGUAS OUTFALL, MONTEVIDEO (URUGUAY)...
INTAKE AND OUTFALL PIPELINES FOR THE SANITATION AND SUPPLY SYSTEM IN T...
MARINE CLIMATE AND DILUTION STUDY TO FIND ALTERNATIVE LOCATIONS FOR TH...