QUAYS

  • Place: Ibiza (Spain)
  • Scope: Design Project for Construction
  • Description:

    3 berthing dolphins are designed to enlarge jetty MT2 so that large Ro/Ro
    and cruise ships could call in Ibiza. The final berthing lengths are 375 m
    on the South side and 328 m on the North side:
    1. Dolphins 1 and 2
            • 17.80 x 28.70 x 2.20 m reinforced concrete deck
            • 16 steel cased reinforced concrete piles
            • 200 t bollards
    2. Dolphin 3
            • 17.80 x 9.80 x 2.50 m reinforced concrete deck
            • 8 steel cased reinforced concrete piles
            • 300 t bollards
    All piles have a diameter of 2 m and their total length is 1835 m. Dolphin
    structures were modelled with SAP2000.
    Design ship data:
            • Loa=339 m
            • B=38.60 m
            • D=8.50 m
            • F=63.70 m
            • Δ=71,000 t


 IMAGES OF THE PROJECT

 
ENLARGEMENT OF THE FIRST JETTY SHELTERED BY BOTAFOC BREAKWATER FOR LARGE SHIPS (IBIZA, SPAIN)
ENLARGEMENT OF THE FIRST JETTY SHELTERED BY BOTAFOC BREAKWATER FOR LARGE SHIPS (IBIZA, SPAIN)
ENLARGEMENT OF THE FIRST JETTY SHELTERED BY BOTAFOC BREAKWATER FOR LARGE SHIPS (IBIZA, SPAIN)

 RELATED PROJECTS

See more projects
ALTERNATIVE CONSTRUCTION PROJECT, SECOND STRETCH OF THE PORT OF GRANAD...
ALTERNATIVE CONSTRUCTION PROJECT FOR THE NORTH-WESTERN QUAY ESPLANADE ...
DESIGN PROJECT OF NORTHERN ENLARGEMENT OF SOUTHERN QUAY, HUELVA...